CategoriesProject Updates

As summer comes to an end and fall arrives, construction activity at Maverick continues at a strong pace. While exterior siding is nearing completion, railings are being installed and landscaping works continues. On the interior, the suites on the upper’s floors are nearing completion with cabinets, countertops and flooring being installed. The building has been connected to permanent power with BC Hydro and the elevator installation is underway.

As we head into the second month of fall, the exterior of the building is nearing completion with final siding being installed and railings being placed on the balconies.  The suites on the upper floors are also near completion too with final painting underway while the suites at the ground level are being drywalled.  Perimeter landscaping continues with placement of the block retaining walls as well as filling the planters with soil in preparation for planting. 

Leave a Reply

Your email address will not be published. Required fields are marked *

Award-winning real estate developer and builder creating innovative, modern-day solutions to housing affordability in British Columbia

Company info

GET IN TOUCH

4631 Shell Rd Suite 185, Richmond, BC
V6X 3M4

+1 604 207 4633

info@tiensher.com

©2023 All rights reserved

Coming Soon

THE MOST EXCITING NEW COMMUNITY IN THE OKANAGAN